SpaceNASA Launch Readiness Reviews

Twenty flashcards on NASA policy NPD 8610.24C: LVRR, FRR, LRR, the Certificate of Flight Readiness and the Final Commit-to-Launch Poll.

Free to start
Your progress here is temporary and is lost when you close this page. Install Making Synapses free to keep it, with spaced repetition.

20 cards
What does NASA certify through its Launch Services Program prelaunch reviews?
Flight readiness of the launch vehicle, payload support hardware and software, and launch site infrastructure.
Name the four LSP prelaunch reviews in NPD 8610.24C.
Launch Vehicle Readiness Review (LVRR), Flight Readiness Review (FRR), Launch Readiness Review (LRR) and the Final Commit-to-Launch Poll.
When is the Launch Vehicle Readiness Review held?
Approximately 30 to 60 days before launch, depending on the launch flow.
What does the LVRR certify?
Readiness to proceed with integrating the spacecraft and the launch vehicle.
Who chairs the LVRR?
The LSP Manager, who reviews any launch vehicle anomalies or issues for the mission.
Where and when is the Flight Readiness Review held?
At the launch site, between 3 and 12 days before launch depending on the launch flow.
Who chairs the FRR?
The NASA Launch Manager (NLM).
What does the FRR certify?
Readiness to start the final launch preparation activities, after closing actions from the LVRR and the spacecraft review.
When is the Launch Readiness Review held?
At the launch site, no later than 1 day before launch.
What does the LRR authorize?
Approval to proceed into the launch countdown.
What document is signed at the end of the LRR?
The Certificate of Flight Readiness (CoFR).
Who signs the CoFR?
The LSP Manager, NASA Spacecraft Mission Director, NLM, launch services contractor representative, LSP technical authorities and a range official.
When is the Final Commit-to-Launch Poll held, and who conducts it?
About 5 minutes before launch, conducted by the NASA Launch Manager.
What is required from everyone polled before terminal count?
A "Go" statement from all parties polled.
Can mandatory launch constraints be waived once terminal countdown starts?
No. They cannot be waived after the start of the terminal launch countdown.
Who gives the spacecraft "Go/No-Go" to the NLM for the final poll?
The NASA Spacecraft Mission Director.
To whom does the NLM give the final launch "Go"?
To the launch services contractor's Launch Director or the appropriate launch crew member.
What plan must the NLM prepare before the LRR?
A pre-mishap plan (formerly the Contingency Action Plan) for the launch-site reaction to a vehicle anomaly and data impoundment.
Who chairs the LRR?
The SOMD Director for Launch Services, or the LSP Manager if the chair is delegated.
What records does the LSP keep after the reviews?
A record of all prelaunch reviews, action item dispositions and the original CoFR; it also documents lessons learned after each mission.

Official sources

National Aeronautics and Space Administration (NASA)

NPD 8610.24C: Launch Services Program Pre-Launch Readiness Reviews

Making Synapses is not affiliated with, sponsored by or endorsed by NASA, the FAA, the Canadian Space Agency or any launch provider. Agency, mission and program names are named only to describe the content.